Advertisement

We need your help now

Support from readers like you keeps The Journal open.

You are visiting us because we have something you value. Independent, unbiased news that tells the truth. Advertising revenue goes some way to support our mission, but this year it has not been enough.

If you've seen value in our reporting, please contribute what you can, so we can continue to produce accurate and meaningful journalism. For everyone who needs it.

Over €13m spent by OPW on controversial Cork flood defence scheme before construction begins

A bitter public dispute and several redesigns have stalled progress and left the city susceptible to flooding.

MORE THAN €13m has been spent on the design and consultation of a controversial flood defence project in Cork in the past eight years.

Despite that extraordinary sum, the final design of the Lower Lee Flood Relief Scheme (LLRFS) is still not decided and construction will not begin until at least mid-2027.

Construction was originally set to begin in 2020 but the Office of Public Works (OPW) denied any project delay, saying “there has been significant enhancements” since it was first exhibited.

This also only represents around 80% of the total project expenditure to date, meaning the total amount spent is likely to be close to €17m.

The project dates as far back as 2006 when flood defences for Ireland’s second largest and most southerly city were proposed as part of a pilot scheme.

This work later transformed into the LLFRS in 2013 when the main agency behind the project, the OPW, proposed investing €140m in flood protection and a further €20m in repairing the city’s history walls.

However, more than a decade on from that, there is little work to show for it as changes in the law as well as a public campaign that proposed an alternative solution resulted in several redesigns and refinements.

As a result, the city remains susceptible to flooding.

The delays have also contributed to increased costs, with the project now expected to cost “at least” €200m for flood protection work as well as the additional €20m for the city walls, according to the OPW.

Two major floods hit Cork in recent memory, first in 2009 and again in 2014, highlighting the need for improvement in flood defences.

The November 2009 flood was described as one of the city’s worst disasters when the River Lee, which flows through the city, burst its banks.

Independent councillor and former Lord Mayor of Cork, Kieran McCarthy, told The Journal Investigates:

Everyone was in shock when that flood happened.

The culmination of weeks of heavy rainfall, high tides and a decision to release the dam further upstream on safety grounds resulted in a torrent of water flooding the city.

Parts of the city were left under one meter of water and one of the city’s hospitals had to be partially evacuated as a result.

More than 60,000 residents were left without drinking water supplies, and up to €130m of damage was caused by the flood, according to the Cork Business Association.

The River Lee burst its banks again in 2014 as the city was battered by a severe storm and heavy rain.

Several parts of the city were left underwater, and hundreds of businesses were flooded once again causing further damage, with many having already been impacted from flooding five years previously.

Between both floods, a reported €140m of damage was caused in Cork.

But almost 20 years since it was first proposed, a flood defence scheme for the city has yet to be agreed.

The Journal Investigates teamed up with media partners in PULSE and the European Data Journalism Network (EDJNet) to investigate how cities, including Cork, have responded to natural disasters.

Data compiled by Spanish outlet El Confidencial shows that the south-west and mid-west of Ireland have experienced the most flood events in the country over the last 150 years.

Investigations like this don’t happen without your support… Impactful investigative reporting is powered by people like you.

A bitter debate over walls

Both major floods reignited the need for flood defences, and the LLFRS project was proposed as a solution to tackle Cork’s multifaceted flooding problem.

However, a bitter debate soon emerged between the OPW and local campaign groups, which centred around the project’s impact on how the city interacted with the river.

Many of the objections to the scheme were due to the various types of barriers and walls proposed. “Impact of proposed walls on heritage and visual” was the top-ranked concern in the scheme’s report following the public exhibition in 2017.

BanksLee-9 The River Lee flowing through Cork City Niall Sargent / The Journal Investigates Niall Sargent / The Journal Investigates / The Journal Investigates

The OPW argued that the project does not propose building high walls along the river and maintains that the works will not block the river from view.

They said that temporary, mountable walled defences are included in the proposals but that these would only be deployed when the risk of flooding is high.

Save Cork City, a campaign group opposed to the project, have consistently argued that the walls scheme will not work and the views of the river in some places will be obstructed.

Instead, the group proposed a tidal barrier downstream of the city as an alternative solution, saying it was more cost-effective and protected the city’s historical aspects.

Councillor McCarthy told us that Cork’s “massive sense of identity and pride” contributed to the heated debate that took place surrounding the proposals.

He admitted that the initial OPW plans “were quite harsh”, but through refinement and public consultation, they were softened.

There were a number of robust conversations between both sides, McCarthy added.

It wasn’t easy on either side, especially in a city that’s very passionate.

In 2019, a presentation given by the OPW to Cork City Council said that the tidal barrier proposal was considered by the organisation but that it would not address the cause of the 2009 flood.

It concluded that a tidal barrier is “neither viable or appropriate for Cork”.

Highlighting the bitterness of the public debate over this project, community groups on both sides declined to speak to our team. One told us this was for fear of relitigating the fierce back and forth that sometimes spilled over into the media.

There was a sense of trauma and old wounds among those involved that they feared would reappear if they discussed the project and their opinions on it.

Final design close to completion

Back in 2013 at the outset of the project, construction was expected to begin towards the end of 2020, however, this timeline was pushed back following the opposition raised during the public exhibition.

The same 2019 presentation to Cork City Council listed early 2021 as the earliest date of construction but noted that there were significant risks of delays arising from judicial review challenges to the scheme.

Since then, the OPW have further revised the timeline, pushing the start of construction back to mid-2027.

Should this timeline be met, 18 years will have passed since the 2009 flood.

However, with many hurdles to clear before reaching that point and the threat of being dragged through the courts still lingering, starting construction in just over two years could be considered optimistic.

A spokesperson for the OPW told The Journal Investigates that “the OPW does not have powers to expedite flood relief schemes”. They added: “The delivery of all schemes must meet all of the regulatory and planning requirements.”

The spokesperson also said the project design hadn’t been delayed, adding that since the public exhibition in 2017, “there has been significant enhancements to the Scheme’s design”.

Some of these changes include addressing the concerns raised by the public and ensuring the project meets the longer-term climate of the city as well as its immediate needs.

However, these enhancements and changes to timelines have led to an increase in the costs associated with the project.

In 2020, when our team investigated the flood scheme previously, the OPW told The Journal Investigates that costs would likely rise from the initially quoted €140m due to inflation.

Today, the OPW expects the project to cost “at least” €200m, a 40% rise. This doesn’t include the additional €20m allocated for repairing the city’s historic walls.

These figures may also rise once again, as the final design of the project will inform the costs of the reworked project.

Other projects impacted too

Additional proposals aimed at protecting other parts of the city from flooding have also faced similar delays due to long legal battles.

The Morrison’s Island Public Realm & Flood Defence Scheme was delayed by several years after Save Cork City challenged the planning application all the way to the Supreme Court before being struck down in 2022.

The project, which is separate from the LLFRS, includes a pedestrian riverside walkway and integrated flood defences for approximately 400 city centre properties. One of the city’s many bridges crossing the Lee will also be replaced and upgraded.

Construction on the project began in July 2024, six years after the project was approved by Cork City Council in 2018. It is expected to take 20 months to complete.

PXL_20250316_135808653 Construction underway on the Morrison's Island Public Realm & Flood Defence Scheme in Cork City Conor O'Carroll / The Journal Investigates Conor O'Carroll / The Journal Investigates / The Journal Investigates

Councillor McCarthy said that the court challenges cost the project two years and that progress had been too slow as a result.

“I think it’s judicial reviews and court proceedings that are holding things up,” he said, which pushed public momentum behind the flood defence projects into other things.

“We just need to get on with it a little bit,” he added.

With the OPW close to finalising the enhancements to the LLFRS, the reluctance to engage in the debate is likely to be challenged soon.

The public will once again be given an opportunity to inspect and comment on the latest evolution of the scheme. A public consultation from the Department of Public Expenditure is expected to be held in late 2025.

This may prove to be the catalyst for reawakening the public debate that never truly went away.

Asked whether getting the Morrison’s Island scheme over the line represents a turning point for the city in terms of opposition to the proposed flood defence schemes, McCarthy pauses before firmly saying “no”.

Why? Because he knows how passionate Cork people are when it comes to changes to the city, he says.

He’s just hoping that another flood doesn’t come down the valley before protections for businesses and homes can be put in place.

The Journal Investigates

This article was produced in the framework of the PULSE initiative as part of the ‘Years After the Disaster’ series, a collaborative project that explores how various European cities have recovered from disasters over time.

You can also read the stories from El Confidencial (Spain), Mediapool (Bulgaria) and HotNews (Romania).

Reporter: Conor O’Carroll • Editor: Maria Delaney • Main Image Design: Lorcan O’Reilly • Social Media: Cliodhna Travers

Investigations like this don’t happen without your support...
Impactful investigative reporting is powered by people like you. Over 5,000 readers have already supported our mission with a monthly or one-off payment. Join them here:

Close
57 Comments
This is YOUR comments community. Stay civil, stay constructive, stay on topic. Please familiarise yourself with our comments policy here before taking part.
Leave a Comment
    Install the app to use these features.
    Mute Seamus Quaide
    Favourite Seamus Quaide
    Report
    Feb 6th 2023, 7:52 AM

    Give us trade and we’ll be fine about you using Shannon Airport for a stopover for your warcrimes in the Middle East.

    170
    Install the app to use these features.
    Mute Kevin Carroll
    Favourite Kevin Carroll
    Report
    Feb 6th 2023, 10:55 AM

    @Seamus Quaide: all our airports are wide open for everyone off the world.
    You don’t need a passboard to get access to Ireland

    98
    Install the app to use these features.
    Mute Sarah Broderick
    Favourite Sarah Broderick
    Report
    Feb 6th 2023, 9:57 AM

    Why bother? Most of the money US companies make in this country doesn’t stay in this country. Are they even making an impact on employment – look at tech???

    102
    Install the app to use these features.
    Mute The next small thing
    Favourite The next small thing
    Report
    Feb 6th 2023, 2:21 PM

    @Sarah Broderick: There are hundreds of thousands working in multinational companies in this country paying a large chunk of payroll taxes and 25% of our overall tax take comes from corporation tax, with the majority coming from a few of these tech/phara compnaies. If these companies stop investing in this country we a banjaxed and there will have to be a large cut in government expenditure to try and balance the budget.

    53
    Install the app to use these features.
    Mute Will Roche
    Favourite Will Roche
    Report
    Feb 6th 2023, 11:19 AM

    Can he not use FaceTime or a phone call?

    89
    Install the app to use these features.
    Mute Rodí O'Leary
    Favourite Rodí O'Leary
    Report
    Feb 6th 2023, 2:40 PM

    @Will Roche: yes, because that’s a great way to build relationships and network… Some expenditure is worth. Not everything can be done on a shoestring.

    35
    Install the app to use these features.
    Mute Johnny Farrell
    Favourite Johnny Farrell
    Report
    Feb 6th 2023, 12:22 PM

    Where are the employees going to live…???

    77
    Install the app to use these features.
    Mute Colm Molloy
    Favourite Colm Molloy
    Report
    Feb 6th 2023, 9:33 AM

    Did he fly direct from Ireland is the question, if not on a state plane

    44
    Install the app to use these features.
    Mute Pat Barry
    Favourite Pat Barry
    Report
    Feb 6th 2023, 9:25 AM

    That’s some jump from 2020 with €50 billion in exports to US! Source CSO.

    21
    Install the app to use these features.
    Mute Pat Barry
    Favourite Pat Barry
    Report
    Feb 6th 2023, 9:52 AM

    @Pat Barry: and €18bn US imports in 2021 so €255bn combined is way off.

    29
    Install the app to use these features.
    Mute Fuji Hakayito
    Favourite Fuji Hakayito
    Report
    Feb 6th 2023, 6:14 PM

    Most politicians I just see as incompetent buffoons. This guy, I dunno, I just don’t like him.

    23
    Install the app to use these features.
    Mute Pat Barry
    Favourite Pat Barry
    Report
    Feb 6th 2023, 6:46 PM

    @Fuji Hakayito: It’s not a popularity show, it’s down to competency as stated and I don’t see him as a buffoon unlike some of his peers.

    15
    Install the app to use these features.
    Mute Patrick Herbert
    Favourite Patrick Herbert
    Report
    Feb 7th 2023, 1:34 PM

    COVENEY IS AT HIS JOB

    1
Submit a report
Please help us understand how this comment violates our community guidelines.
Thank you for the feedback
Your feedback has been sent to our team for review.

Leave a commentcancel